Status of August 2009  
 

Jump to
Detailed Progress

1.1 Progress Photo and Key Plan

1.2 Executive Summary of Monthly Event
          The cumulative progress details for main sections of the Contract are listed as follows (base on planned of rev.3 update no.2 as data cut off dated 17.05.2008 and change order no.51 as 01.07.2009) :
Diversion Dyke and Coffer Dams
Cumulative progress of the works in this section is 100%. (U/s Coffer Dam filling completed upto EL.558.00m on dated 15 July 2009)
Main Dam
Cumulative progress of the works in this section is 51.44% compared with the target of 78.55%, 27.11% behind schedule.
Approach Channel & Decanting Basin
Cumulative progress of the works in this section is 95.47% compared with the target of 91.72%, 3.42% ahead schedule.
Power Intake
Cumulative progress of the works in this section is 66.64% compared with the target of 100%, 33.36% behind schedule.
Spillway Crest, Chute & Plunge Pool
Cumulative progress of the works in this section is 66.01% compared with the target of 98.87%, 32.86% behind schedule.
Excavation at Powerhouse
Cumulative progress of the works in this section is 99.83% compared with the target of 100%, 0.17% behind schedule.
Switchyard
Cumulative progress of the works in this section is 99.69% compared with the target of 94.72%, 4.97% ahead schedule.
Grouting & Drainage Galleries
Cumulative progress of the works in this section is 66.70% compared with the target of 84.94%, 18.24% behind schedule.
Bottom Outlet Works
Cumulative progress of the works in this section is 25.36% compared with the target of 22.00%, 3.36% ahead schedule.

Current Status*
          The construction in the period of Monthly Progress Report No. 69 is from August 1, 2009 to August 31, 2009. The overall progress of this period is as follows:

 
This month
Accumulated to this month
Actual Work Progress - 66.72%

1.3 Total Work Progress
- Summary of Total Work Progress - August 2009
- Summary Work Progress base on Revised Programme L2-Network Rev. 3.0 Dated July 31, 2006 Updated No.2 (Rev 3.2 as 17 May 2008)

1.4 Contractor Organization Chart - August 2009

1.5 Weather and Water Level Record - August 2009

 
Copyright © 2008 ITD-KOLDAM, All right reserved.
Italian-Thai Development Public Company Limited (J.1479)
Kyan, P.O. Slapper, Teh. Sunder Nagar, Distt. Mandi, Himachal Pradesh, India 174403
Email : admin@itd-koldam.com, Fax : +91 981-6093252